SPECIAL SUPPLEMENT

 

 

 

 

District Government of Tharparkar

2-YEARS ACHIVEMENT OF DISTRICT GOVERNMENT THARPARKAR IN FOCUS 

During last two years District Government Tharparkar has under gone tremendous development activities under the dedicated leader ship of Arbab Anwar, Zila Nazim Tharparkar. The said activities are basically aimed at to provide maximum level of facilities to the down trodden people of Tharparkar in all respects and without any discrimination. The details are as under:

 

Budget Position

Year 2006-6  2006-07

Year 2007-08

Sector

No of

Scheme

Allocation

Sector

No of

Scheme

Allocation

Agriculture

06

19.967 (M)

Agriculture

14

83.910 (M)

PP&H

28

63.903 (M)

PP&H

23

108.435 (M)

Health

12

52.572 (M)

Health

07

31.963 (M)

S. Welfare.

05

30.512 (M)

S-Welfare

04

5.600 (M)

Education Versions Porg:

33

151.430 (M)

Education Versions Porg:

40

291.194 (M)

I.T

-

 

I.T

01

12.000 (M)

Rural Dev:

81

286.531 (M)

Rural Dev:

122

660.894 (M)

F&P

-

 

F&P

01

2.000 (M)

W/S & Drainage

30

69.732 (M)

W/S & Drainage

39

113.317 (M)

CCB Schemes

1.34

58.303 M

CCB Schemes

200

75.000 (14

Total

 

732.950

Total

 

1384.313

 

Current - Expenditure 2006-07

Salary

Non-Salary

Total

1187.342 (M)

459.360 (M)

1646.72 (M)

 Schemes Executed Under Provincial Highway Division Thar @ Mithi

1

No. of Schemes

56 Nos

2

Approved Cost

22518.21 (Million)

3

Approve Length

Construction: 1954.50 KM, Improved: 81.50 KM

4

Expenditure upto 30-06-2007

2901.3715 (M)

5

Completed Scheme (Road in length)

Construction: 278 KM, Improved: 23 KM, Blacktop (DST): 65 KM

6

Allocation 2007-08

1943.671 (M)

7

Released 2007-08 upto September

293.813 (M)

8

Expenditure upto September

196-79 (M)

9

Target upto June 2008

Construction: 241.0 KM, Improvement: 25.0 KM


President General Pervaiz Musharraf accompanying Chief Minister Dr. Arbab Ghulam Rahim, Dr. Hamida Khuhro and Arbab Anwar the Zila Nazim exchanging view in a meeting at Historic Naukot Fort.

 

TOTAL DISTRICT GOVERNMENT BUDGET 2007-08 = 3031.015

Physicial & Financial Progess 2006-07

PSDP

Sector

No. of Scheme

No. of Units

Funds released

Upto June -07

% Utilization

Physical Progress in

Agriculture

06

20

17.667

17.667

100%

56%

PP&H

25

49

51.825

49.271

98%

52%

Health

11

19

41.848

31.121

74%

62%

S.Welfare

05

99

29.765

29.565

99%

99%

Education

31

2138

109.953

107.800

99%

80%

Rural Dev:

70

70

277.179

275.717

99%,

33%

W/s & Drainage

30

107 Wells

13 W / S

1 Brick Pavent

1 Drainage

122

69.732

69.732

100%

50%

CCB

134

134

58.303

58.303

100%

100%

SDSSP

Education

03

23

6.374

6.374

100%

84%

Health

02

04

14.973

13.020

88%

88%

PROVINCIAL SCHEME

Education

15

186

89.122

89.122

100%

42%

Health

1

1

6.396

6.396

100%

100%

PP&H

1

1

1.318

1.318

100%

100%

C.M DIRECTIVES

Education

04

13

6.082

6.082

100%

100%

Roads

16

16

89.600

84.673

95%

95%

Rural Dev:

04

04

25.941

25.941

100%

100%

P.M DIRECTIVES

Road

1

1

19.157

19.157

100%

100%

MPA

Priority

Program

18

130

9.7 13

9.713

100%

70%

KKP

15

44

38.927

38.927

100%

100%

 

 

VISION OF ZILA NAZIM THARPARKAR FOR THE YEAR 2007-08

 

Sector

Ongoing Schemes

Near Schemes

Cost

Status

Agriculture

Construction and Establishment of 19 Veterinary extension Center in District Tharparkar

-

28.103

Finishing in progress

Construction of A riculture Com lex

-

8.432

Roof laid

Construction of Endo & Ecto Parasites in livestock at 3 Model Villages District Tharparkar.

-

4.500

5000 Animal drenched

Tree Plantation in Model Villages & Mithi Town

 

3.000

Target of 10000 Plants achieved

Establishment of Demonstration plots in different field and frout fieldd in District Th.axparkar

-

1.500

Work in Progress

 

Installation of Electric Water lifting machine at progressive farmer field in. District Tharparkar

5.000

Under Approval Process

 

Establishment of 3 Units Cattle Colonies in District Tharparkar

20.000

Under Approval Process

 

Construction of

Veterinary Center in District Tharparkar

10.000

Under Approval Process

 

Honey Bee keeping     on farmer field in District Tharparkar I

2.000

Under Approval Process

 

Strengthening of 2 Veterinary Mobile Units in District Tharparkar

8.000

Under approval process

PP&H

 

 

Construction of 7 beded rest house

 

11.072

Completed

Construction of 3 units residential Ben-glows

 

8.527

Roof laid

Construction of Musafarkhana 2 Units

 

1.538

Finishing in progress

Construction of Education Complex

 

11.255

Roof laid m

Construction of Huts shads Hotel & Rest house @ Gadi Hill point

 

19.974

Finishing in Progress

Construction of office & residence of DDOs

 

19.886

Completed

Construction of Shopping center at Marvi Lodge Mithi

 

15.143

Roof laid

Construction of Shopping Center & Motel in Mithi Town

 

18.492

Roof laid

 

Construction of Residence Benglow 4 units

10.400

Under approval process

 

Construction of Guest House Cum Hostel (10 beded in Nagarparkar)

5.000

Under approval process

 

Socio Economic Center in Mithi Town

3.000

Under approval process

 

Construction of Shopping Center in Mithi Town 2 Units

10.000

Under approval process

 

Construction of Main Entry Gate 2 Nos

10.000

Under approval process

 

Establishment of Gamekhana at Gadi Hill point Mithi

5.000

Under approval process

Health

Up gradation of BHU Kot Arbab Mir Muhammad

 

30.762

Completed

Construction of CCU & ICU Units

 

19.337

Roof laid

Construction of Medical Dispensary 5 Units

 

9.835

Completed

 

Hepatitis Control Program its District Tharaarkar

10.000

Approved

 

Up gradation of Civil Hospital Taluka Hospitals

10.000

Approved

Social

Welfare

 

Construction of Community Centers 7S Units        

35.141

Completed

 

Construction of Computer Center for Women for designing handicrafts 5 Units

2.400

Un-Approved

 

Construction of Library in Mithi Town

6.000

Un-Approved

Information

Technology

 

Introduction of Information

Technology in District Tharparkar

12.000

Approved

Planning & Financing

 

Capacity Building for Officers / Officials of all group of Offices

5.000

Un-approved

Education

Construction of 2 Roomed / 1 roomed shelterless schools (497 Units)

 

186.591

Completed

Construction of Boundary wall & other missing facility (146 Units)

 

46.062

Completed

Rehabilitation of Primary School (107 Units)

 

17.125

Completed

 

Construction of 1 roomedShelterless Primary school in District Tharparkar (230 Units)

42.000

Un-approved

 

Up-gradation of Primary School to Middle Schools (12 units)

2.000

Un-approved

 

Up-gradation of Middle School to High School in District Tharparkar (5 units)

20.000

Un-approved

 

Construction of Compound wall Lavatory Block in Primary School (40 Units)

5.000

Un-approved

Road

209 KMs

 

971.996

Completed

 

129 KMs

557.000

Approved

 

 