|
RBOD: a potential threat to Amri relics
Today in southwestern Sindh, the Right Bank
Outfall Drainage-extension canal is being dug from Sehwan Sharif
to Gharo, and on its way it is running through the unique and
internationally recognized archeological site of Amri, cir. 3,400
BCE.
By Sameeta Ahmed
“Amri represents a complete story of the beginning,
development and decline of the world-famous Indus Valley Civilization.
It must be protected at all costs,” according to Dr. M. Rafique
Mughal, Professor of Archaeology and Heritage Management at Boston
University, and former Director-General of Archaeology and Museums
in Pakistan. Culturally, Amri's earliest levels are linked with
the earliest cultures of the Indus Valley and Balochistan with
Radiocarbon dates going back to 3,400 BCE. The settlement continued
during the time of Moenjodaro (2500 -2000/ 1500 BCE) and was re-inhabited
during the Islamic period. In the 1920s the Archeological Survey
of India excavated distinct polychrome ceramic wares here with
similarities found in adjoining sites. The site was re-excavated
by a French team in the 1960s. In these modest-sized mounds, layers
of remnant stone masonry, burnt clay brick (of unique historic
dimensions), mud brick and ceramic wares have been found, even
in the limited area of the excavations conducted until now. 'Amri
Culture' became a term used by archeologists to denote the settlements
and culture in the region that predated even Moenjodaro.

The set of archeological remains at Amri forms
a “protected site” listed with the Federal Government's Department
of Archaeology (DOA) thus any new development in its surrounds
is legally required by the Antiquities Act-1975 to stay clear
of it by 200 feet. However, the Right Bank Outfall Drain (RBOD),
a venture of the Irrigation and Power Department, Government of
Sindh, was planned to run directly between the two main mounds
of the site. According to DOA sources, the RBOD Environmental
Impact Assessment (EIA) team on its own was not referring to,
and accommodating in their design proposal the 'protected monuments
list' as they are legally required to by the Environmental Protection
Agency (EPA). But at the last minute, while the RBOD's EIA was
being prepared and when they were alerted by the DOA about the
official protected status of the site, the RBOD project authorities
presented two other options for realigning the canal path in December
2002. The drain could be looped wide around the mounds towards
the Indus River to leave the required 200 feet, a considerably
more expensive option. Or, it could be placed on the other side,
tightly between the adjacent Indus Highway and Mound B, leaving
barely 10 feet between the drain canal and the visible rise
of the mound, but still seeming to 'save the mounds' from the
originally planned direct hit, even if it was still violating
the 200 feet clause. However, considerable damage has already
occurred at the site, with the canal excavation cutting across
the immediate periphery of the base of the mound. It is a given
in archeology that this kind of a mound is just the tip of the
iceberg indicating a larger body of historic habitation remains
below, and the remains exposed and 'run over' at this spot are
testimony to this. So, in effect, the 10 feet buffer is not protecting
the remains at all, it is merely not touching the small tip above
ground level, and even that will ultimately be damaged when the
canal starts operating.
This highway-side option, officially leaving
the '10 foot buffer', was adopted in the design of the project,
with RBOD project authorities claiming that there was an unwritten
'understanding' with the DOA that this was acceptable. The DOA
asserts that even then, there was a stipulation on its part that
it would base its decision on an archeological Salvage Excavation
that it would conduct. If this investigation revealed previously
unexcavated historic material of 'positive significance' on that
highway-side edge of the site, the route would have to be reconsidered.
However, the drainage canal actually started being dug out on
that side before the DOA's Salvage Excavation took place there
in May-June 2006, and its report submitted by the Exploration
and Excavation Branch to the Islamabad head office in October
2006. One assumes that the apparently 'significant' finds of the
archeological investigation are the basis for which the DOA says
that it has still not granted the final, official 'written' NOC
required by the RBOD project. However, the Salvage Excavation
Report is not being made public by DOA high-ups, and has not even
been officially shared with the department's own Director in Sindh.
Legally, the EPA's 'Guidelines for Sensitive
Critical Areas' have to be followed in any development project
design and considered in its Environmental Impact Assessment before
project approval by the government agency. These Guidelines include
a listing of the federal DOA's officially protected historic sites
that must be respected under the framework of the Antiquities
Act of 1975. If the project design simply follows the guidelines
and does not show any intrusion upon the sites, the EPA directly
grants approval. Only if there is an unusual case demanding special
attention, is the Director-General of the DOA consulted for 'determining
the allowable degree of development', based on his discerning
judgment and reasons which do not have to be officially disclosed.
Without the NOC having been issued by the Director-General-DOA
to the RBOD project, after its case was brought to his attention,
the construction at Amri should not have begun at all.
RBOD authorities claim that they 'will continue
with work' regardless, since 'a realignment has already been made
in the project to accommodate the site'. Considerable damage is
already done, but if the Drain construction is completed and it
actually starts functioning, the thousands of cusecs of flow will
soon inundate the rest of the mound, regardless of assurances
by project authorities that a 'CC lining' especially provided
on that strip would stop seepage.
At Amri, a furlong away from the banks of the
Indus is the original cultural landscape of an important phase
in history. The drastic RBOD canal-building will completely destroy
this precious world-class site and its setting irreversibly. We
cannot afford to lose one of the world's oldest heritage sites.
(Sameeta Ahmed, Architect, NED, Karachi).
|